| DATE | ACTIVITY |
| Feb 2004 |
Architect Selection |
| March - May 2004 | Building Investigation and Inspection by Architect with Consultants and District personnel |
| May 2004 | Board Decision to not build new facility but to relocate to David Avenue site. |
| Sept - Oct 2004 | Preparation of base drawings. Architect work with site committee to develop project "Scope of Work." |
| Nov 2004 | Board concurrence with "Scope of Work" |
| Nov 2004 | Finalization of plans and submittal to State for approvals |
| Dec 2004 - Jan 2005 | State Review/Revision/Authorization |
| Feb 2005 | Board Authorization to Bid |
| March 2005 | Project Bid |
| April 2005 | Project Award (subject to funds availability) |
| May 2005 | Preliminary construction work begins |
| June 2005 | Major construction begins |
| August 2005 | Major construction ends. |
| October 2005 | Project completion |