Pacific Grove High School Phased Project Schedule |
| PHASE I - General Site Work (Except elevator) | |
| Nov 1, 2000 | Submit Phase I to DSA |
| Jan 1, 2001 | Receive DSA backcheck comments |
| Jan 15, 2001 | DSA Approval |
| Out to Bid | |
| Feb 27, 2000 | Open Bids |
| Mar 1, 2001 | Award Contract |
| May 16, 2001 | Start Construction-Partial Site Access |
| June 9, 2001 | Major Construction Start |
| Aug 15, 2001 | Major Construction Complete (Full Occupancy) |
| Sept 15, 2001 | Complete Construction |
| PHASE II - Phased Building Improvements and Elevator (updated 2002) | |
| Mar 1, 2001 | Submit Phase II to DSA |
| June 1, 2001 | DSA backcheck comments |
| July 1, 2001 | DSA Approval |
| Submit to California Department of Education | |
| July 15, 2001 | Approval from California Department of Education |
| Submit to OPSC | |
| Aug 15, 2001 | OPSC Authorization to Bid |
| Jan 31, 2002 | Board Authorization to Bid |
| Feb 4, 2002 | First Advertisement to Bid |
| Feb 11, 2002 | Second Advertisement to Bid |
| Feb 14, 2002 | Pre-Bid Walk-Through (2:00 PM) |
| March 12, 2002 | Open Bids (2:00 PM) |
| March 21, 2002 | Board Award of Bids |
| March 22, 2002 | Notice to Proceed |
| March 28, 2002 | Pre-Construction Conference |
| March 29, 2002 | Contract Executed |
| April 1, 2002 | Start of Construction |
| June 10, 2002 | Major Construction Activity Start |
| Aug 16, 2002 | Major Construction Activity Complete |
| Aug 19, 2002 | Teachers Return |
| Aug 20, 2002 | Students Return |
| Oct 28, 2002 | Project Completed |
Questions and Comments to webmaster@pgusd.org
updated: 3/4/2002