PHASE I - General Site Work (Except elevator)
Nov 1, 2000 Submit Phase I to DSA
Jan 1, 2001 Receive DSA backcheck comments
Jan 15, 2001 DSA Approval
  Out to Bid
Feb 27, 2000 Open Bids
Mar 1, 2001 Award Contract
May 16, 2001 Start Construction-Partial Site Access
June 9, 2001 Major Construction Start
Aug 15, 2001 Major Construction Complete (Full Occupancy)
Sept 15, 2001 Complete Construction
   
PHASE II - Phased Building Improvements and Elevator (updated 2002)
Mar 1, 2001 Submit Phase II to DSA
June 1, 2001 DSA backcheck comments
July 1, 2001 DSA Approval
  Submit to California Department of Education
July 15, 2001 Approval from California Department of Education
  Submit to OPSC
Aug 15, 2001 OPSC Authorization to Bid
Jan 31, 2002 Board Authorization to Bid
Feb 4, 2002 First Advertisement to Bid
Feb 11, 2002 Second Advertisement to Bid
Feb 14, 2002 Pre-Bid Walk-Through (2:00 PM)
March 12, 2002 Open Bids (2:00 PM)
March 21, 2002 Board Award of Bids
March 22, 2002 Notice to Proceed
March 28, 2002 Pre-Construction Conference
March 29, 2002 Contract Executed
April 1, 2002 Start of Construction
June 10, 2002 Major Construction Activity Start
Aug 16, 2002 Major Construction Activity Complete
Aug 19, 2002 Teachers Return
Aug 20, 2002 Students Return
Oct 28, 2002 Project Completed