Pacific Grove Middle School Phased Project Schedule |
| DATE | ACTIVITY |
| Feb 4, 2002 | Complete construction documents and submit to the Division of State Architect |
| June 3, 2002 | Return comments received from DSA, Start plan check corrections |
| June 24, 2002 | DSA Plan check corrections re-submitted and approved |
| Jan 9, 2003 | Board approval to Bid Project |
| Feb 3, 3003 | Out to bid, first advertisement |
| Feb 10, 2003 | Second advertisement for bidding |
| Feb 13, 2003 | Pre-construction walk-through at site. |
| Mar 4, 2003 | Open bids |
| Mar 20, 2003 | District approval of bids |
| Mar 21, 2003 | Notice to proceed |
| Mar 31, 2003 | Start Construction |
| June 9, 2003 | Start major construction |
| Aug 4, 2003 | Administrative Staff returns |
| Aug 15, 2003 | Complete major construction |
| Aug 18, 2003 | Teachers return |
| Aug 19, 2003 | Students return |
| Oct 24, 2003 | Complete Construction |