Project Schedule (revised 6/04)
(based on current understanding of required timelines and funding availablity)

DATE ACTIVITY
Jan/Feb
2003
Architect Selection
Feb/March
2003
Building Investigation and Inspection by Architect with Consultants and District personnel
March/May
2003
Preparation of base drawings. Architect work with site committees to develpe project "Scope of Work."
June 2003 Board concurrence with "Scope of Work"
June 2003 Finalization of plans and submittal to State for approvals
July 2003-
March 2004
State Review/Revision/Authorization
March 2004 Board Authorization to Bid
March -May
2004
Project Bid (re-bid required)
June 2004 Project Award to DMC Construction
June 2004 Major construction begins
August 2004 Major construction ends.
October 2004 Project completion