1. PG Middle School
Modernization
|
- Contract was awarded to Sanchez construction and work is complete.
- Project includes items such as replacing heating system, upgrading electric, re-roofing, repairing restrooms, and improving accessibility with walkways and an addition lift.
- Funding Measure A - $3.0 million.
|
|
2. Forest Grove
Modernization Phase II
|
- Contract awarded to DMC construction work began Summer 2003 and was completed Fall 2003.
- Project included work on classroom Building G and multipurpose room stage-includes items such as replacing heating system, upgrading electrical, repairing restrooms.
- Funding Measure A - $400,000.
|
|
3. Robert Down
Modernization
|
- Contract was awarded to DMC Construction. Work began Summer 2004 and completed February 2005.
- Project included items such as replacing heating system, upgrading electrical, renovating restrooms, re-roofing, improving accessibility.
- Funding Measure A-$2.5million
|
|
4. PG High School
Modernization Phase III
|
- Projects are being completed over two years. (2003/04 and 2004/05)
- Projects completed include replacing HS Gym bleachers, K/L wing lighting change, replace bell system, complete door/hardware upgrade, repair kitchen floor , library carpeting.
- Projects in process ( summer/fall 2005) include classroom floor covering, (Contractor - DMC) window repairs ( Contractor - Baptista) and exterior painting ( Contractor Theodorapoulos).
- Funding Measure A - $800,000
|
|
5. Community HS
|
- Project design approved by State.
- Project includes remodeling of four classrooms at David Avenue school site.
- Construction contract awarded to Baptista - work in progress - Summer 2005.
- Funding Measure A-$200,000
|