Pacific Grove Unified School District
Pacific Grove Middle School
Phased Project Schedule

DATE ACTIVITY
Feb 4, 2002 Complete construction documents and submit to the Division of State Architect
June 3, 2002 Return comments received from DSA, Start plan check corrections
June 24, 2002 DSA Plan check corrections re-submitted and approved
Jan 9, 2003 Board approval to Bid Project
Feb 3, 3003 Out to bid, first advertisement
Feb 10, 2003 Second advertisement for bidding
Feb 13, 2003 Pre-construction walk-through at site.
Mar 4, 2003 Open bids
Mar 20, 2003 District approval of bids
Mar 21, 2003 Notice to proceed
Mar 31, 2003 Start Construction
June 9, 2003 Start major construction
Aug 4, 2003 Administrative Staff returns
Aug 15, 2003 Complete major construction
Aug 18, 2003 Teachers return
Aug 19, 2003 Students return
Oct 24, 2003 Complete Construction